Assignments span a 30-GW renewable energy plant, four transmission projects and airport expansions in three cities.
AECOM (NYSE: ACM) has been appointed to provide program management services across three Adani Group infrastructure programs in India, covering renewable energy generation, electricity transmission and airport infrastructure. The projects have a combined capital investment of approximately $15 billion, according to AECOM
The assignments spans Gujarat, Maharashtra, Karnataka and Kerala, giving the infrastructure consultancy responsibilities across multiple stages of India’s energy and aviation infrastructure development.
Khavda project leads energy program
AECOM will serve as program management consultant for the 30-gigawatt Khavda Renewable Energy Plant in Gujarat. The project combines solar and wind generation with battery energy storage systems, bringing multiple power technologies into a single large-scale development.
The scale of the project also requires substantial supporting transmission infrastructure to evacuate electricity from renewable generation sites to consumption centers. This connection becomes particularly important as large renewable energy projects add capacity to India's electricity network.
Adani Green Energy (NSE: ADANIGREEN), which is developing the Khavda project, reported that operational capacity at the site reached 9.4 GW as of March 31, 2026. The developer said it commissioned 5.1 GW during fiscal 2025-26 and is targeting completion of the full 30-GW project by 2029.
Transmission projects strengthen grid connectivity
A second assignment covers four transmission and substation projects across Gujarat and Maharashtra. According to AECOM, the projects are intended to strengthen the transmission network and establish a green energy corridor linking renewable generation hubs with high-demand locations, including Mumbai.
The transmission component addresses a separate requirement of India's energy transition: expanding renewable generation capacity is not sufficient without the infrastructure to move electricity to where it is needed. Substations and transmission lines form part of that wider network, allowing electricity generated at renewable energy sites to enter the grid and reach consumers.
Together, the Khavda and transmission assignments place AECOM across both renewable power generation and supporting grid infrastructure. However, the announcement did not provide individual project capacities, locations of the substations or construction schedules.
Airport assignments cover three cities
The third program involves airport modernization and expansion in Ahmedabad, Mangaluru and Thiruvananthapuram. AECOM will provide program-wide management, coordination and delivery oversight for the infrastructure work.
All three airports are part of Adani Airport Holdings' portfolio. The projects are intended to increase passenger capacity, improve airport facilities and strengthen regional connectivity, according to AECOM.
The airport assignments extend the consultancy's role beyond energy infrastructure into aviation, where expansion programs require coordination across passenger facilities and other airport infrastructure. AECOM's announcement, however, did not specify the planned capacity additions, individual modernization packages or investment allocated to each airport.
Contract details and delivery timelines remain undisclosed
The three programs represent approximately $15 billion in combined capital investment, but AECOM did not disclose the value of its own program management contracts. The announcement also did not specify when its assignments would begin or provide completion dates for the transmission and airport projects.
The distinction is important because the investment figure represents the estimated capital commitment across the infrastructure programs, not AECOM's contract revenue.
The appointments place AECOM across several parts of Adani Group's infrastructure development in India, linking large-scale renewable energy generation with the transmission systems needed to distribute electricity and airport infrastructure intended to support passenger growth. The extent of AECOM's contractual responsibilities and the projects' individual delivery schedules will become clearer as further details are disclosed.